Winter Works 2018/19 & Lock Closures

29/10/2018 @ 12:00 am - 15/3/2019 @ 12:00 am

Event Navigation

29 October 2018 to 1 March 2019 – Molesey Lock – Work Complete
Replacing the timber sheeting on the face of each lock gate. Completed and lock re-opened.

7 January 2019 to 15 March 2019 – Caversham Lock
(Passage may be possible from February 2019)
Refurbishing the lock chamber’s concrete walls and timber edging. Replacing the wet boat shed roller shutter doors upstream of the lock.

29 October 2018 to 15 March 2019 – Teddington Lock (launch)
Refurbishing the lock chamber concrete walls and replacing the lock side rubbing timbers and bollards.

25 January 2019 to 10 February 2019 – Cookham Lock – Work Complete
Refurbishing the concrete sill of the tail lock gates.
Crompleted and lock re-opened

1 December 2018 to 1 March 2019 – Rushey Lock – Work Complete
Replacing the timber sheeting on the face of each lock gate.
Completed and lock re-opened